Blockchain Reporter Sep 8, 2026

Soluna Completes 83 MW Kati 1 Bitcoin Hosting Site

Soluna Completes 83 MW Kati 1 Bitcoin Hosting Site

Soluna Holdings said on Sept. 8 that it energized the final 14 megawatts at Project Kati 1 in Texas, completing the 83 MW Bitcoin-hosting site.

The milestone lifts the company’s total operating capacity to approximately 206 MW and closes the first phase of a planned 166 MW computing campus.

In its project update, Soluna also said the Electric Reliability Council of Texas conditionally classified the entire Kati campus as Base Load in its Batch Zero interconnection process. That designation includes Kati 1 and the planned 83 MW Kati 2 expansion.

Final 14 MW completes the first phase Soluna said every phase of Kati 1 was delivered on schedule and that infrastructure costs remained on budget. Energization began in February after ERCOT approval.

This page shows the RSS-provided summary/preview. Full publisher content remains available at the original source.